Timeline

RERA registeredApr 2020
Proposed completionDec 2023
TodayJul 2026
Construction progress
Storm Water Drains0%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Sewerage (Chamber,…100%
Landscaping & Tree…100%
Street Lighting100%
Water conservation…100%
Energy managemcnt100%
Fire protection an…100%
Electrical meter r…100%
Aggregate area of …100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Raghvendra Buildcon

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
1City
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
69 homeson the public record across 2 projects
7,126 sq mbuilt-up filed
9,200 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimpri Chinchawad (M Corp.)
Taluka
Haveli
District
Pune
Pincode
411062
Survey no.
Gat No. 114
North boundary
Gat no 113
East boundary
Gat no 110
South boundary
Gat No 119 and Gat no 120
West boundary
18 Meter Road
What’s nearby
SchoolsNearest school 1.8km away · College or university 1.3km away
HealthcareHospital 424m away · 3 clinics within 1km
LifestyleNo parks within 2km · 5 restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Convenience store within 1km
Getting around
Expressway 2.3 km · Western Express HighwayPrimary road 534 m · Adi Sankaracharya Marg FlyoverRailway line 3.2 km · Western Railway (Slow)Metro station 485m away (SEEPZ)Bus stop within 1km
Water & environment
Water body 274 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpari Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Gat No. 114

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpari Chinchwad Municipal Corporation

Municipal corporation

Has approved 31 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
30
On record
707 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.