HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
1 units
Saleable area
129–130 sq mper unit, as filed
Floors
5
Land area
372 sq m
Built-up area
1,327 sq m

Timeline

RERA approvedJul 2022
Proposed completionJul 2028
TodayJul 2026
Construction progress

23.5% overall, as filed

Basement & plinth0%
Podiums0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Stilt floor40%
Superstructure45%
Stairs & lifts50%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.
02

Builder’s track record

RERA Telangana · Promoter registration

Shashikiran Builders & Developers

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
2Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
20 homeson the public record across 2 projects
3,137 sq mbuilt-up filed
966 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Kompally
Village
Kompally-Ncl Colony
Mandal
Dundigal Gandimaisamma
District
Medchal-Malkajgiri
Pincode
500014
North boundary
Plot No 7
East boundary
Plot No 15
South boundary
Plot No 8
West boundary
12m wide Road
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.7km away
HealthcareHospital 76m away · 2 clinics within 1km
LifestyleNo parks within 2km · 6 restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · ATM within 500m
Getting around
Expressway 126 m · Nizamabad RoadPrimary road 3.8 kmRailway line 2.6 kmRailway station 3.0km away (Bolarum)Limited bus connectivity nearby
Water & environment
Water body 726 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 006143/BP/HMDA/1211/MED/2022Survey no. 183/C and 190
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 006143/BP/HMDA/1211/MED/2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.