Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
75–95 sq mper unit, as filed
Floors
5
Land area
595 sq m
Built-up area
1,810 sq m

Timeline

RERA approvedSep 2018
Proposed completionSep 2024
TodayJul 2026
Construction progress

41% overall, as filed

Basement & plinth0%
Podiums0%
Flat fit-out0%
OC-readiness0%
Internal finishes40%
External finishes45%
Stairs & lifts50%
Superstructure75%
Excavation100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
SK AKHILLAM II12BHK951 of 1
SK AKHILLAM II12BHKmortgaged931 of 1
SK AKHILLAM II12BHKmortgaged752 of 2
SK AKHILLAM II22BHK951 of 1
SK AKHILLAM II22BHK931 of 1
SK AKHILLAM II22BHK752 of 2
SK AKHILLAM II32BHK951 of 1
SK AKHILLAM II32BHK931 of 1
SK AKHILLAM II32BHK752 of 2
SK AKHILLAM II42BHK951 of 1
SK AKHILLAM II42BHK931 of 1
SK AKHILLAM II42BHK752 of 2
SK AKHILLAM II52BHK951 of 1
SK AKHILLAM II52BHK931 of 1
SK AKHILLAM II52BHK752 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SHASHIKIRAN BUILDERS & DEVELOPERS

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
2Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
20 homeson the public record across 2 projects
3,137 sq mbuilt-up filed
966 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
jeedimetla village 1
Village
Jeedimetla-Village
Mandal
Qutballapur
District
Medchal-Malkajgiri
Pincode
500055
North boundary
neighbours land
East boundary
neighbours land
South boundary
road
West boundary
road
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.7km away
HealthcareHospital 707m away · 2 clinics within 1km
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km
ShoppingSupermarket 620m away · Mall 776m away · Bank 830m away
Getting around
Expressway 2.9 km · Nizamabad RoadPrimary road 708 m · Jeedimetla Main RoadRailway line 3.4 kmRailway station 4.0km away (Suchitra Centre)Limited bus connectivity nearby
Water & environment
Canal 1.4 km
distances only — not a flood assessment
Declared external development
Water supply30%
Lift30%
Electricity10%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan
Building Permit
Survey no. 238/2

The promised possession date (27 Sep 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.