HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
93–96 sq mper unit, as filed
Floors
5
Land area
608 sq m
Built-up area
1,890 sq m

Timeline

RERA approvedFeb 2019
Proposed completionApr 2021
TodayJul 2026
Construction progress

1.6% overall, as filed

Basement & plinth0%
Podiums0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation6%
Stilt floor10%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
AKSHITA HEIGHTS TWO TOWER-II12BHK961 of 1
AKSHITA HEIGHTS TWO TOWER-II12BHK933 of 3
AKSHITA HEIGHTS TWO TOWER-II22BHKmortgaged933 of 3
AKSHITA HEIGHTS TWO TOWER-II22BHK961 of 1
AKSHITA HEIGHTS TWO TOWER-II32BHK933 of 3
AKSHITA HEIGHTS TWO TOWER-II32BHK961 of 1
AKSHITA HEIGHTS TWO TOWER-II42BHK933 of 3
AKSHITA HEIGHTS TWO TOWER-II42BHK961 of 1
AKSHITA HEIGHTS TWO TOWER-II52BHK933 of 3
AKSHITA HEIGHTS TWO TOWER-II52BHK961 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

AKSHITA AVENUES LLP

LLPPromoter type
Medchal-Malkajgiri, TelanganaBased in
3Projects
1City
2019–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
125 homeson the public record across 3 projects
13,188 sq mbuilt-up filed
5,634 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MALKAJGIRI
Village
Anand Bagh
Mandal
Malkajgiri
District
Medchal-Malkajgiri
Pincode
500047
North boundary
ROAD AND NEIGHBOURS LAND
East boundary
30 FEET WIDE ROAD
South boundary
RESIDENTIAL PREMISES NO 24-142-2A
West boundary
RESIDENTIAL PREMISES NO 24-141-1A
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.1km away
HealthcareHospital 417m away · 1 clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.2km away
ShoppingSupermarket 1.0km away · Bank 713m away
Getting around
Primary road 1.2 kmRailway line 218 mRailway station 1.1km away (Safilguda)Bus stop within 1km
Water & environment
Water body 1.1 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 39

The promised possession date (30 Apr 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.