HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
2
Parking
35 spaces
Land area
745 sq m

Timeline

RERA registeredOct 2020
Proposed completionDec 2023
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

ROHINTON MEHTA CONSTRUCTIONS MUMBAI

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2020–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Andheri
Taluka
Andheri
District
Mumbai Suburban
Pincode
400069
Survey no.
CTS 749 - 749-1 TO 749-11
North boundary
PLOT NO 60
East boundary
ROAD
South boundary
PLOT NO 58
West boundary
WESTREN RAILWAY LINE
What’s nearby
Schools2 schools within 500m · 3 educational institutions within 1km · Library 1.9km away
HealthcareHospital 281m away · 27 clinics within 1km · Pharmacy within 500m
LifestylePark 528m away · Gym or sports centre 1.7km away · 22+ restaurants and cafes within 1km
ShoppingSupermarket 478m away · Convenience store within 500m · Bank 409m away
Getting around
Expressway 802 m · Andheri FlyoverPrimary road 291 m · G K Gokhale FlyoverRailway line 108 mRailway station 251m away (Andheri)9 bus stops within 500m
Water & environment
Water body 1.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. CTS 749 - 749-1 TO 749-11

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.