HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
61
Buildings
10
Parking
853 spaces
Land area
11,011 sq m
Sanctioned built-up
1,11,324 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2024
TodayJul 2026
Construction progress
Club House Level 1…0%
Fire Protection an…0%
Fitness Centre0%
Landscaping and Tr…0%
Club House Level 2…0%
Treatment and disp…0%
Storm Water Drain0%
Water Conservation…0%
Electrical Meter R…0%
Sewerage0%
Club House0%
Community Building…10%
Landscaping & Tree…15%
Flat fit-out19%
Street Lighting30%
Ammenity Floor Wom…32%
Fire protection an…33%
Electrical meter r…33%
Sports Pavillion S…35%
Water Supply50%
Sewerage (Chamber,…50%
Treatment And Disp…50%
Solid Waste Manage…50%
Water conservation…50%
Internal finishes66%
OC-readiness68%
Storm Water Drains80%
External finishes87%
Podiums95%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Internal Roads & F…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ERA REALTORS PRIVATE LIMITED

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2017–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Borivali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400097
Survey no.
811 A/7pt 812 813 814 A/1 to A/4 821pt 824pt 825pt 844pt
North boundary
CTS 825pt 811A6
East boundary
CTS 805
South boundary
CTS 823 817
West boundary
Western Express Highway
What’s nearby
Schools2 schools within 1km · College or university 1.5km away
HealthcareHospital 272m away · 7 clinics within 1km
LifestylePark 640m away · Gym or sports centre 486m away · 4 restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Mall 685m away
Getting around
Expressway 55 mPrimary road 1.3 km · Swami Vivekanand RoadRailway line 1.1 km · Western Railway Virar to BorivaliMetro station 384m away (Kurar)Limited bus connectivity nearby
Water & environment
Water body 126 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. 811 A/7pt 812 813 814 A/1 to A/4 821pt 824pt 825pt 844pt

The promised possession date (30 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation20 cases on record, earliest 2012
Compliance51 non-compliance notices on record
Appeals27 appeals before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

253 complaints on MahaRERA’s register for this project 237 disposed, 16 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.