Complete project overview

MahaRERA · Registration filing
Floors
31
Buildings
2
Parking
249 spaces
Land area
11,540 sq m
Sanctioned built-up
11,540 sq m

Timeline

RERA registeredMay 2024
Proposed completionDec 2030
TodayJul 2026
Construction progress
Podiums0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Superstructure50%
Stairs & lifts50%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Internal Roads & F…100%
Sewerage (Chamber,…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RAJ CORPORATION

PartnershipPromoter type
Thane, MAHARASHTRABased in
7Projects
6Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
686 homeson the public record across 7 projects
38,834 sq mbuilt-up filed
40,923 sq mland declared
₹29.23 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 3 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporationthis project1 of 3 projects
Uvarsad Gram Panchayat, Uvarsad1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
KACHORE
Taluka
Kalyan
District
Thane
Pincode
421203
Survey no.
S. N. 31/Hissa No. 6A,6B & 7
North boundary
Noorani
East boundary
Road
South boundary
Community Hall
West boundary
Husami
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 949m away · Clinic within 2km
LifestylePark 1.2km away
ShoppingSupermarket 1.4km away
Getting around
Expressway 2.5 km · Chhatrapathi Shivaji Maharaj BridgePrimary road 601 m · Kalyan - Shil RoadRailway line 932 mRailway station 1.9km away (Thakurli)Limited bus connectivity nearby
Water & environment
Water body 1.5 km · Ganesh Visarjan Talao,Thakurli
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S. N. 31/Hissa No. 6A,6B & 7
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.