HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
50 spaces
Land area
3,645 sq m
Sanctioned built-up
2,772 sq m
Recreational open space
849 sq m

Timeline

RERA registeredMar 2020
Proposed completionJan 2024
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

PANDHARINATH SITARAM PATIL

IndividualPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2020–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400605
Survey no.
CTS NO.1721/A,B1,B2,B3,B4,B5
North boundary
812 1813
East boundary
25 Mt DP ROAD CTS NO 1721 B2
South boundary
1754
West boundary
CTS NO 1721 A
What’s nearby
Schools1 school within 1km · College or university 1.1km away · Library 1.3km away
HealthcareHospital 781m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 1.8km away · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Convenience store within 1km · Bank 514m away
Getting around
Expressway 2.6 kmPrimary road 138 m · Thane Belapur RoadRailway line 459 m · Trans-Harbour LineRailway station 1.2km away (Kalva)5 bus stops within 500m
Water & environment
Water body 687 mRiver 699 m · Thane Creek
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. CTS NO.1721/A,B1,B2,B3,B4,B5

The promised possession date (30 Jan 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.