HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
77 spaces
Land area
4,000 sq m
Sanctioned built-up
3,416 sq m
Recreational open space
311 sq m

Timeline

RERA registeredOct 2020
Proposed completionJun 2025
TodayJul 2026
Construction progress
Stilt floor0%
Open Parking50%
Water Supply60%
Storm Water Drains60%
Landscaping & Tree…60%
Street Lighting60%
Energy managemcnt60%
Electrical meter r…75%
Aggregate area of …75%
Sewerage (Chamber,…90%
Fire protection an…90%
Internal Roads & F…95%
Treatment And Disp…95%
Water conservation…95%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

AMBROSIA LANDMARK PRIVATE LIMITED

CompanyPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2020–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Hadapsar
Taluka
Haveli
District
Pune
Pincode
411028
Survey no.
177/2B
North boundary
Adjoining Survey No 177 PATR
East boundary
Adjoining Survey No 177PART
South boundary
18M Existing DP Road
West boundary
12M Proposed Road
What’s nearby
Schools1 school within 1km · Library 1.2km away
HealthcareHospital 570m away · 4 clinics within 1km
Lifestyle1 park within 500m · Gym or sports centre 1.2km away · 3 restaurants and cafes within 1km
ShoppingSupermarket 334m away · Bank 737m away · ATM within 500m
Getting around
Expressway 460 m · Mundhwa RoadPrimary road 1.5 km · Mundhwa RoadRailway line 919 m · Pune - Daund Railway LineRailway station 1.4km away (Hadapsar Railway Station)Limited bus connectivity nearby
Water & environment
Water body 243 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

A

Building Permit
Survey no. 177/2B

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.