HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
5
Parking
20 spaces
Land area
1,116 sq m
Sanctioned built-up
2,497 sq m
Recreational open space
1,291 sq m

Timeline

RERA registeredJun 2024
Proposed completionNov 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

LANJILE ESTATE

CompanyPromoter type
Latur, MAHARASHTRABased in
1Projects
1City
2024–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Khadgaon
Taluka
Latur
District
Latur
Pincode
413512
Survey no.
Plot No.4A, Survey No.34/B/2
North boundary
9 Mtr Wide Road
East boundary
Plot No 3
South boundary
Land in Sy No 35
West boundary
Plot No 5B
What’s nearby
Schools1 school within 500m · College or university 1.4km away
HealthcareHospital 1.1km away · Clinic within 2km
LifestylePark 705m away · Gym or sports centre 1.3km away · Swimming pool within 2km
ShoppingSupermarket 1.2km away
Getting around
Expressway 1.2 kmPrimary road 194 m · New Barshi RoadRailway line 3.2 kmRailway station 3.8km away (Latur Railway Station)Limited bus connectivity nearby
Water & environment
Canal 1.7 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Collector Office Latur

Collector office
Building Permit
Survey no. Plot No.4A, Survey No.34/B/2

The promised possession date (21 Nov 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.