01

Complete project overview

MahaRERA · Registration filing
Floors
19
Buildings
2
Parking
1 spaces
Land area
2,263 sq m
Sanctioned built-up
10,565 sq m

Timeline

RERA registeredJun 2023
Proposed completionDec 2027
TodayJul 2026
Construction progress
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
OC-readiness60%
Flat fit-out75%
External finishes80%
Basement (if any)90%
Podiums90%
Plinth90%
Stilt floor90%
Internal finishes95%
Excavation100%
Superstructure100%
Stairs & lifts100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

HARIOM DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
8Projects
5Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
339 homeson the public record across 8 projects
22,260 sq mbuilt-up filed
7,923 sq mland declared
₹13.34 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Bhavnagar Municipal CorporationMunicipal / Corporation2 of 5 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 5 projects
Navi Mumbai Municipal CorporationMunicipal Corporationthis project1 of 5 projects
Others1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Navi Mumbai (M Corp.)
Taluka
Thane
District
Thane
Pincode
400706
Survey no.
PLOT NO.24,SEC-29,NERUL EAST
North boundary
PLOT NO 23
East boundary
15 MTR EXISTING ROAD
South boundary
PLOT NO 25
West boundary
RAILWAY CORRIDOR
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 121m away · 2 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 277m away · 20+ restaurants and cafes within 1km
ShoppingSupermarket 293m away · Mall 1.8km away · Convenience store within 500m
Getting around
Expressway 1.2 km · Amra MargPrimary road 1.2 km · Palm Beach MargRailway line 44 m · Trans-Harbour LineRailway station 1.6km away (Seawoods)12 bus stops within 500m
Water & environment
Water body 745 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Navi Mumbai Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO.24,SEC-29,NERUL EAST
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Navi Mumbai Municipal Corporation

Municipal corporation

Has approved 121 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
105
On record
1,099 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.