Complete project overview

MahaRERA · Registration filing
Floors
26
Parking
36 spaces
Land area
882 sq m
Sanctioned built-up
1,050 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2018
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Muktistar Buildcon Private Limited VISHWANATH GAIKWAD

IndividualPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2017–2018Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Borivali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400067
Survey no.
1/C/1/231 / PLOT NO 156
North boundary
BY PROPERTY BEARING CTS NO-154
East boundary
BY 13 METER WIDE - 7TH ROAD
South boundary
CTS-158 9 METER WIDE RSC-34
West boundary
BY PROPERTY BEARING CTS-364 CTS-35
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.7km away
HealthcareHospital 374m away · 6 clinics within 1km · Pharmacy within 1km
LifestylePark 995m away · Gym or sports centre 650m away · 14+ restaurants and cafes within 1km
ShoppingSupermarket 548m away · Mall 585m away · Bank 548m away
Getting around
Expressway 3.3 km · Western Express HighwayPrimary road 546 m · Goregaon Link RoadRailway line 2.1 kmMetro station 548m away (Kandivali (West))Bus stop within 1km
Water & environment
Water body 615 m · gorai creek drain
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. 1/C/1/231 / PLOT NO 156

The promised possession date (31 Dec 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Appeals1 appeal before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

4 complaints on MahaRERA’s register for this project 4 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.