The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location
MahaRERA · Registration filing
Village
Khaire
Taluka
Shahapur
District
Thane
Pincode
421601
Survey no.
Sr.No75/B, Plot No.127 & 128
North boundary
Tilak Construction co
East boundary
Ansal House Limited
South boundary
Jagan Budhela
West boundary
Sunil Kabra
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.7 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 2.0 kmRiver 2.3 km
distances only — not a flood assessment
Location — done
04
Government Guidance Rate
Maharashtra IGR — Annual Statement of Rates
In Maharashtra it’s called the ready reckoner rate.
₹26,338per sq yd
₹31,500per sq m
Which rate
residential building or flat
Matched to
The rate published for the village of “Khaire”.
In force
2026-2027 schedule
What this number is — and isn’t
The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
MahaRERA · Approved building plan
Collector Office, Thane
Collector office
Building Permit
Survey no. Sr.No75/B, Plot No.127 & 128
The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
The planning authority
The body that approved this project. It has approved 4,607 RERA projects across 33 districts — about 1 in 4 in Maharashtra.
Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
A disposed complaint may have been resolved for or against the builder, and only disputes escalated to MahaRERA appear here at all.
Number
Date
Status
CC12504283
4 Dec 2025
Order Approveddisposed
What the builder declared
Declared to MahaRERA
Litigation
None declared to MahaRERA
The builder's own declaration at registration — not a court's or MahaRERA's finding. A flagged line is worth checking with MahaRERA.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with MahaRERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
66 residential projects still under way within 25 km. Step out ring by ring:
Of the 9 projects the radar draws within 6 km — every kind, every stage — none is a residential project still under way. This list keeps only those, and looks further out.
44 projects between 10 and 20 km — showing the nearest 6.
11.2 km awayResidential / Group Housing
Pool City Lakshadweep Villa
Meravilla Infra Private Limited · Vafe · Shahapur
3 yr 6 mo
Jun 2025registered
Dec 2028target completion
Government Guidance Rate₹34,281/sq ydScale81 flatsAuthorityMahaRERA