PR1270002501600 · MahaRERA · https://gethorizon.in/projects/aqua-suites-bagmala-alibag-jj9boap3

01

Complete project overview

MahaRERA · Registration filing
Units
150 units
Floors
19
Buildings
2
Parking
291 spaces
Land area
23,136 sq m
Sanctioned built-up
10,174 sq m

Timeline

RERA registeredNov 2025
Proposed completionDec 2030
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Excavation4%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Dynamix Vacation Resorts Private Limited

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
8Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
480 homes · 164 plotson the public record across 8 projects
44,918 sq mbuilt-up filed
70,055 sq mplotted area
1,62,599 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Asst Director Town Planning Authority Alibaugthis project3 of 7 projects
Town Planning Department Raigad3 of 7 projects
Assistant Director Town Planning Authority Raigad Alibaug1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Dynamix Vacation Resorts Private Limited— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Bagmala
Taluka
Alibag
District
Raigarh
Pincode
402204
Survey no.
RZ06, Gut No 3/1/5
North boundary
INTERNAL DRIVEWAY
East boundary
INTERNAL DRIVEWAY
South boundary
INTERNAL DRIVEWAY
West boundary
INTERNAL DRIVEWAY
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 586 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 720 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹32,943per sq yd
₹39,400per sq m
Which rate
residential building or flat
Matched to
The rate published for the village of “Bagmala”.
In force
2026-2027 schedule

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Asst Director Town Planning Authority Alibaug

Building Permit
Survey no. RZ06, Gut No 3/1/5
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

87 residential projects still under way within 25 km. Step out ring by ring:

Of the 25 projects the radar draws within 6 km — every kind, every stage — 5 are residential projects still under way. This list keeps only those, and looks further out.

4 projects within 3 km — showing the nearest 4.

750 m awayOthers

CERULEAN PHASE 1

SWAROOP S REVANKAR · Palav · Alibag

Mar 2026registered
Dec 2028target completion
Scale26 flatsAuthorityMahaRERA
1.5 km awayResidential / Group Housing

Aqua Vista

Dynamix Vacation Resorts Private Limited · Bagmala · Alibag

Sep 2025registered
Dec 2030target completion
Government Guidance Rate₹32,943/sq ydScale64 flatsAuthorityMahaRERA
1.5 km awayResidential / Group Housing

Aqua Bliss

Dynamix Vacation Resorts Private Limited · Bagmala · Alibag

Sep 2025registered
Dec 2030target completion
Government Guidance Rate₹32,943/sq ydScale64 flatsAuthorityMahaRERA
1.5 km awayResidential / Group Housing

Aqua Shores

Dynamix Vacation Resorts Private Limited · Bagmala · Alibag

Sep 2025registered
Dec 2030target completion
Government Guidance Rate₹32,943/sq ydScale202 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.