01
Complete project overview
MahaRERA · Registration filing- Floors
- 6
- Buildings
- 4
- Parking
- 78 spaces
- Land area
- 8,430 sq m
- Sanctioned built-up
- 5,589 sq m
Timeline
RERA registeredOct 2023
Proposed completionJun 2030
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Open Parking0%
Internal finishes1%
Stairs & lifts15%
Podiums75%
Superstructure75%
Basement (if any)85%
Excavation100%
Plinth100%
Stilt floor100%
02
Builder’s track record
MahaRERA · Promoter registrationEMPIRE ARENA
PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Thane (M Corp.)
- Taluka
- Thane
- District
- Thane
- Pincode
- 400612
- Survey no.
- 134/1, 134/2/A AND 136
- North boundary
- SURVEY NO 137 AND 138
- East boundary
- 60 METER WIDE DP ROAD
- South boundary
- SURVEY NO 133
- West boundary
- SURVEY NO 137 AND 138
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.0km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 63 mPrimary road 1.1 km · Shil Phata Mahape RoadRailway line 3.3 km · Mumbai-Pune RailwayRailway station 3.9km away (Diva Junction)2 bus stops within 500m
Water & environment
Water body 831 m
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
1 complaint on MahaRERA’s register for this project — 1 disposed.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.