Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
110 units
Mix
56 × 1 BHK · 48 × 2 BHK · 6 × Shop
Carpet area
9–51 sq mper-unit range, as filed
Floors
6
Buildings
4
Parking
17 spaces
Land area
4,255 sq m
Sanctioned built-up
5,231 sq m
Recreational open space
426 sq m

Timeline

RERA registeredAug 2018
Proposed completionJun 2026
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

110 units across 25 batches
TypeArea sq mCount
1 BHK382
1 BHK384
1 BHK392
1 BHK374
1 BHK374
1 BHK374
1 BHK362
1 BHK362
1 BHK384
1 BHK384
1 BHK3416
1 BHK384
2 BHK4816
2 BHK4816
1 BHK384
2 BHK512
2 BHK512
Shop102
2 BHK514
Shop92
Shop102
2 BHK482
2 BHK482
2 BHK512
2 BHK502

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Arihant Vastu Nirman Pvt. Ltd

CompanyPromoter type
Ratnagiri, MAHARASHTRABased in
11Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
815 homeson the public record across 11 projects
64,259 sq mbuilt-up filed
48,127 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Chiplun Municipal Council ChiplunMunicipal Councilthis project1 of 4 projects
Chiplun Municpal Council1 of 4 projects
Ratnagiri Municipal Corporation RatnagiriMunicipal Corporation1 of 4 projects
Ratnagiri Municipal CouncilMunicipal Council1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Chiplun (M Cl)
Taluka
Chiplun
District
Ratnagiri
Pincode
415604
Survey no.
Survey No. 188 Hissa No. 5/1
North boundary
CTS No 6340
East boundary
CTS No 6336 6334
South boundary
Internal Road
West boundary
CTS No 6338 6301
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 213m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Expressway 367 mRailway line 2.1 kmRailway station 2.1km away (Chiplun)Bus stop within 500m
Water & environment
River 395 mWater body 1.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Chiplun Municipal Council Chiplun

Municipal Council
Building Permit
Survey no. Survey No. 188 Hissa No. 5/1

The promised possession date (1 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.