Complete project overview

MahaRERA · Registration filing
Floors
35
Buildings
2
Parking
182 spaces
Land area
3,442 sq m
Sanctioned built-up
13,610 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2021
TodayJul 2026
Construction progress
Podiums0%
Treatment And Disp…0%
Water Supply50%
Sewerage (Chamber,…50%
Storm Water Drains50%
Internal finishes55%
Flat fit-out55%
Stairs & lifts55%
External finishes55%
OC-readiness55%
Superstructure60%
Fire protection an…60%
Electrical meter r…70%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ZEUS HOUSING COMPANY

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2017–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mumbai City
Taluka
Mumbai City
District
Mumbai City
Pincode
400013
Survey no.
88
North boundary
BMC SCHOOL
East boundary
RAILWAY BOUNDARY
South boundary
C S NO 89
West boundary
N M JOSHI MARG
What’s nearby
Schools2 schools within 1km · College or university 1.4km away
HealthcareHospital 696m away · 3 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.8km away · Gym or sports centre 1.6km away · 24+ restaurants and cafes within 1km
ShoppingSupermarket 328m away · Bank 64m away · ATM within 500m
Getting around
Expressway 1.0 km · Dr Babasaheb Ambedkar MargPrimary road 8 m · Senapati Bapat MargRailway line 354 mRailway station 405m away (Lower Parel)6 bus stops within 500m
Water & environment
Water body 669 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 88

The promised possession date (30 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.