HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
4
Parking
60 spaces
Land area
1,195 sq m
Sanctioned built-up
4,316 sq m

Timeline

RERA registeredOct 2025
Proposed completionMar 2028
TodayJul 2026
Construction progress
Excavation0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Aggregate area of …0%
Superstructure20%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ASHTAVINAYAK DEVELOPERS

PartnershipPromoter type
Nashik, MAHARASHTRABased in
12Projects
10Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
879 homes · 91 plotson the public record across 12 projects
40,137 sq mbuilt-up filed
88,961 sq mland declared
₹95046.10 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 7 projects
ChhindwaraTown & Country Planning (DTCP)1 of 7 projects
Metro Nagpur Improvement Trust1 of 7 projects
Nashik Municipal CorporationMunicipal Corporationthis project1 of 7 projects
Others1 of 7 projects
Pune Municipal CorporationMunicipal Corporation1 of 7 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik (M Corp.)
Taluka
Nashik
District
Nashik
Pincode
422003
Survey no.
PLOT NO 10+11+12, S NO 277/1/3
North boundary
9 MT WIDE ROAD
East boundary
PLOT NO 13 AND 9
South boundary
9 MT WIDE ROAD
West boundary
12 MT WIDE ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away · Clinic within 2km
LifestylePark 1.9km away
ShoppingNo supermarket within 2km
Getting around
Expressway 2.4 kmPrimary road 414 m · Dr Nanasaheb Dharmadhikari MargNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 76 mRiver 921 m · Waghadi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nashik Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO 10+11+12, S NO 277/1/3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nashik Municipal Corporation

Municipal corporation

Has approved 821 RERA projectsabout 1 in 24 in Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
692
On record
4,331 flats · 111 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.