HORIZONMarkets
Registration de-registered

MahaRERA has de-registered this project — the registration was cancelled. This is a serious signal: the project is no longer under active RERA registration. Do not transact without independent legal verification of what happened and where the project stands.

01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
10
Parking
96 spaces
Land area
2,799 sq m
Sanctioned built-up
5,988 sq m

Timeline

RERA registeredMay 2024
Proposed completionDec 2028
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Yogesh Pramodshankar Desai

IndividualPromoter type
Nandurbar, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nandurbar (M Cl)
Taluka
Nandurbar
District
Nandurbar
Pincode
425412
Survey no.
S. No. 273/1, Plot No. 27, 28, 29, 30, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73 at Bypass Road, Yogi Nagar, Nandurbar 425412
North boundary
Plot No 74 and 75
East boundary
9 Mtr Road
South boundary
15 Mtr Road
West boundary
12 Mtr Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 958m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 125 mPrimary road 1.3 kmRailway line 716 mRailway station 1.8km away (Nandurbar)Limited bus connectivity nearby
Water & environment
Water body 3.1 kmRiver 3.4 km · Sukal Nala
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

The Office Of Munciple Coorporation Of Nandurbar

Building Permit
Survey no. S. No. 273/1, Plot No. 27, 28, 29, 30, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73 at Bypass Road, Yogi Nagar, Nandurbar 425412
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.