HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
13
Buildings
2
Parking
120 spaces
Land area
692 sq m
Sanctioned built-up
1,735 sq m

Timeline

RERA registeredDec 2023
Proposed completionSep 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Fire protection an…0%
Electrical meter r…0%
OC-readiness50%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ATLANTA BUILDCON

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ulhasnagar (M Corp.)
Taluka
Ulhasnagar
District
Thane
Pincode
421002
Survey no.
CTS NO 30966 30967 4954 4955 30885 30886 U NO 97 98 99 SHEET NO 71
North boundary
BEWAS CHOWK
East boundary
ROAD
South boundary
CTS NO 2608
West boundary
BARRACK NO 327 DHOLARAM DARBAR
What’s nearby
Schools1 school within 1km
HealthcareHospital 256m away · 2 clinics within 1km
LifestylePark 591m away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.5 km · Ahilyanagar - Kalyan Road | Bhiwandi - Murbad Road | B K Birla RoadPrimary road 383 m · Kalyan Badlapur RoadRailway line 978 m · Mumbai-Pune RailwayRailway station 1.3km away (Vithalwadi)Limited bus connectivity nearby
Water & environment
Water body 287 mRiver 567 m · Waldhuni River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Ulhasnagar Municipal Corporation

Municipal Corporation
Building Permit
Survey no. CTS NO 30966 30967 4954 4955 30885 30886 U NO 97 98 99 SHEET NO 71
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Ulhasnagar Municipal Corporation

Municipal corporation

Has approved 37 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
32
On record
283 flats · 0 plots
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.