HORIZON
Share

ATMATARA

PRGO01190691 · RERA Goa · https://gethorizon.in/projects/atmatara-south-goa-z6yd27pv

01

Complete project overview

RERA Goa · Registration filing
Project name
ATMATARA
Units
14 units
Mix
14 × Flats
Land area
930 sq m
Covered area
284 sq m
Open area
646 sq m
Parking
14 spaces
Description
RESIDENTIAL

Timeline

Project startedNov 2018
Proposed completionDec 2020
TodaySep 2026

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

14 units across 1 batch
TypeArea sq mCount
Flats6314

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Goa · Builder registration

SAIYED JABBAR ABDUL

IndividualPromoter type
South Goa, GoaBased in
1Projects
1Cities
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Goa · Registration filing
Address
Date of Registration :
District
South Goa
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 959m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 494m away
Getting around
Expressway 1.6 kmPrimary road 903 m · Margaon Ponda State HighwayNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 1.2 km
distances only — not a flood assessment
04

Government Guidance Rate

Goa registration department

In Goa it’s called the notified land rate.

No government guidance rate is shown for this project.

Goa notifies its land rates taluka by taluka, and this project doesn't name the ward or survey number the order prices — so no figure is shown rather than a neighbouring zone's.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RERA Goa · Approved building plan
Building Permit

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

07

Other projects nearby

The register · within 25 km

65 residential projects still under way within 25 km. Step out ring by ring:

23 projects within 1 km — showing the nearest 6.

South GoaMixed Development

AMBA HILLS

ANAND B. DALAL

PossessionDec 2026Scale14 flatsAuthorityRERA Goa
South GoaMixed Development

AMBI EVERGREEN

YALLAPA B AMBI

PossessionOct 2028Declared cost₹3.99 CrScale9 flats
South GoaResidential/Group Housing

AMBA HILLS BLOCK B

SONALI NIKHIL PAI

PossessionDec 2026Declared cost₹14.44 CrScale20 flats
South GoaResidential/Group Housing

CASA DE NAGOA

NITIN KUMAR AGARWAL

PossessionFeb 2027Declared cost₹11.89 CrScale14 flats
South GoaResidential/Group Housing

ASHIRWAD CHAVADI RESIDENCY Phase 2

LEO CONSTRUCTION BUILDER AND REAL ESTATE DEVELOPERS Proprietor Mr SHIVANAND K AMONKAR

PossessionFeb 2029Declared cost₹1.11 CrScale8 flats
South GoaMixed Development

ENJEE PRIME COLONY PHASE - I

NIKITA SUDESH GADKAR

PossessionJun 2028Declared cost₹4.65 CrScale14 flats

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Goa does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Goa does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — RERA Goa does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.