Complete project overview

RERA Chhattisgarh · Registration filing
Units
3 units
Quarterly reports
14 on filequarterly progress reports filed with RERA

Timeline

RERA registeredAug 2018
Proposed completionAug 2021
TodayJul 2026
Construction progress

100% overall, as filed

Internal Roads And Footpaths100%
Water Supply100%
Sewerage100%
Storm Water Drains100%
Landscaping And Tree Planting100%
Street Lighting100%
Open Parking100%
Community Buildings100%
Treatment And Disposal Of Sewerage And Sullage Wat100%
Solid Waste Management And Disposal100%
Water Conservation Rain Water Harvesting100%
Energy Maanagement100%
Fire Protection And Fire Safety Requirements100%
Boundary Wall100%
Security Service100%
Gym100%
Place Of Worship100%
Swimming Pool100%
Club House100%
From the promoter's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

RERA Chhattisgarh · Promoter registration

Skyline infra

Partnership FirmPromoter type
8Projects
7Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
123 homes · 34 plotson the public record across 8 projects
22,838 sq mbuilt-up filed
11,084 sq mland declared
₹79.85 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
BhopalTown & Country Planning (DTCP)1 of 6 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 6 projects
Nagpur Minicipal Corporation1 of 6 projects
Surat Municipal CorporationMunicipal / Corporation1 of 6 projects
Thane Municipal CorporationMunicipal Corporation1 of 6 projects
Wardha Municipal CouncilMunicipal Council1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Chhattisgarh · Registration filing
District
Bilaspur
Tehsil
Bilaspur
Address
VILLAGE :- LINGIYADIH, BILASPUR (C.G.)
What’s nearby
Schools4 schools within 500m · 4 educational institutions within 1km · College or university 1.5km away
HealthcareNearest hospital 2.3km away
Lifestyle3 parks within 500m · Gym or sports centre 1.4km away
ShoppingNo supermarket within 2km
Getting around
Expressway 441 m · SIPAT ROADPrimary road 102 mRailway line 4.0 kmRailway station 4.1km away (Bilaspur Junction)Limited bus connectivity nearby
Water & environment
Water body 1.1 km · Nagin Naag TalaabRiver 1.7 km · Arpa
distances only — not a flood assessment
Land, title & encumbrance
Mortgage2 unit(s) declared under mortgage to a bank/lender for project finance
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹30.53 Cr declared to build 3 flats. What that works out to:

₹10.18 Crdeclared cost per flatall-in — land + construction
6%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

Complaints register

None on record with RERA Chhattisgarh against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.