HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
30
Buildings
2
Parking
57 spaces
Land area
2,341 sq m
Sanctioned built-up
13,056 sq m

Timeline

RERA registeredDec 2024
Proposed completionMar 2029
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Storm Water Drains0%
Fire protection an…0%
Electrical meter r…0%
Water conservation…5%
Internal finishes8%
Stairs & lifts8%
Superstructure17%
Water Supply19%
Sewerage (Chamber,…34%
Stilt floor45%
Basement (if any)87%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SKYLINE INFRA

PartnershipPromoter type
Nagpur, MAHARASHTRABased in
8Projects
7Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
123 homes · 34 plotson the public record across 8 projects
22,838 sq mbuilt-up filed
11,084 sq mland declared
₹79.85 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
BhopalTown & Country Planning (DTCP)1 of 6 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 6 projects
Nagpur Minicipal Corporationthis project1 of 6 projects
Surat Municipal CorporationMunicipal / Corporation1 of 6 projects
Thane Municipal CorporationMunicipal Corporation1 of 6 projects
Wardha Municipal CouncilMunicipal Council1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nagpur (M Corp.)
Taluka
Nagpur (Urban)
District
Nagpur
Pincode
440008
Survey no.
AMALGAMATED PLOT NO. 247, 248, 272 and 273, IN CENTRAL ROAD SECTION III SCHEME, KH. NO. 44, CTS. NO. 329, SHEET NO. 34, WARD NO. 21, EAST WARDHMAN NAGAR MOUZA-PARDI
North boundary
9 MTR WIDE ROAD
East boundary
PLOT NO 249 271
South boundary
12 MTR WIDE ROAD
West boundary
PLOT NO 246 274
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 276m away · 2 clinics within 1km
LifestylePark 1.2km away
ShoppingNo supermarket within 2km
Getting around
Expressway 116 m · FlyoverPrimary road 110 m · Old Bhandara RoadRailway line 1.2 kmMetro station 256m away (Vaishnodevi Square)Limited bus connectivity nearby
Water & environment
River 753 m · Naag RiverWater body 885 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nagpur Minicipal Corporation

Building Permit
Survey no. AMALGAMATED PLOT NO. 247, 248, 272 and 273, IN CENTRAL ROAD SECTION III SCHEME, KH. NO. 44, CTS. NO. 329, SHEET NO. 34, WARD NO. 21, EAST WARDHMAN NAGAR MOUZA-PARDI
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.