Complete project overview

MahaRERA · Registration filing
Floors
28
Buildings
2
Parking
80 spaces
Land area
1,657 sq m
Sanctioned built-up
6,409 sq m
Recreational open space
342 sq m

Timeline

RERA registeredOct 2018
Proposed completionOct 2024
TodayJul 2026
Construction progress
Flat fit-out0%
Internal Roads & F…0%
Water Supply0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
External finishes10%
OC-readiness10%
Internal finishes35%
Sewerage (Chamber,…40%
Superstructure90%
Stairs & lifts95%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ASAYA BUILDERS AND DEVELOPERS LLP

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2018–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Navi Mumbai (M Corp.)
Taluka
Thane
District
Thane
Pincode
400703
Survey no.
P-KK-8-25
North boundary
PLOT NO - 26 AND 27 AND 28 AND 29 AND 30
East boundary
3 M WIDE PATHWAY 6 M WIDE ROAD
South boundary
15 M WIDE ROAD
West boundary
PLOT NO - 24
What’s nearby
Schools1 school within 1km
HealthcareHospital 418m away · 3 clinics within 1km
LifestylePark 551m away · Gym or sports centre 720m away · 12+ restaurants and cafes within 1km
ShoppingSupermarket 310m away · Convenience store within 500m · Bank 603m away
Getting around
Primary road 312 m · Thane Belapur RoadRailway line 192 mNo metro or railway within 5kmBus stop within 500m
Water & environment
Water body 271 m · GANPATI VISARJAN POND KK
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Navi Mumbai Municipal Corporation

Municipal Corporation
Building Permit
Survey no. P-KK-8-25

The promised possession date (30 Oct 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Navi Mumbai Municipal Corporation

Municipal corporation

Has approved 121 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
105
On record
1,099 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Compliance1 non-compliance notice on record
Appeals1 appeal before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

4 complaints on MahaRERA’s register for this project 2 disposed, 2 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.