HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
142 spaces
Land area
2,184 sq m
Sanctioned built-up
5,094 sq m
Recreational open space
393 sq m

Timeline

RERA registeredNov 2019
Proposed completionSep 2023
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
OC-readiness0%
Internal Roads & F…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Water Supply50%
Sewerage (Chamber,…50%
Fire protection an…50%
External finishes75%
Stairs & lifts90%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Shree GHP Housing

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2019–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400601
Survey no.
28 and 36 Tika No.5
North boundary
CTS No-27
East boundary
CTS No-36 and road
South boundary
CTS No 29-30-31-34-35
West boundary
CTS No-26
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 3.5 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 442 m · KolvanCanal 993 mWater body 1.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation Thane

Municipal Corporation
Building Permit
Survey no. 28 and 36 Tika No.5

The promised possession date (15 Sep 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation Thane

Municipal corporation

Has approved 19 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
13
On record
74 flats · 0 plots
Since
2018

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.