Complete project overview

MahaRERA · Registration filing
Units
31 units
Mix
17 × Shop · 14 × 2 BHK
Carpet area
9–59 sq mper-unit range, as filed
Floors
7
Parking
7 spaces
Land area
543 sq m
Sanctioned built-up
1,391 sq m

Timeline

RERA registeredJan 2022
Proposed completionDec 2026
TodayJul 2026
Construction progress
Water Supply0%
Water conservation…0%
Electrical meter r…0%
Basement (if any)1%
Podiums1%
Plinth1%
Superstructure6%
Stilt floor23%
Excavation100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

31 units across 14 batches
TypeArea sq mCount
2 BHK582
2 BHK584
2 BHK592
Shop201
2 BHK586
Shop231
Shop91
Shop161
Shop161
Shop171
Shop201
Shop181
Shop223
Shop186

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

VIJAYRAJ ENTERPRISES

PartnershipPromoter type
Solapur, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Solapur (M Corp.)
Taluka
Solapur North
District
Solapur
Pincode
413224
Survey no.
PLOT NO 23
North boundary
9M ROAD
East boundary
DP ROAD
South boundary
PLOT NO 22
West boundary
PLOT NO 16 17 AND 18
What’s nearby
SchoolsNearest school 1.9km away · College or university 1.8km away
HealthcareHospital 862m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 1.3km away
Getting around
Expressway 4.1 km · Siddheshwar Temple RoadPrimary road 1.7 km · Kumathe- Aherwadi RoadRailway line 706 mRailway station 2.4km away (Tikekarwadi)Bus stop within 500m
Water & environment
Water body 2.2 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.