01

Complete project overview

MahaRERA · Registration filing
Plots
36 plots
Land area
12,716 sq m

Timeline

RERA registeredJul 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Landscaping & Tree…0%
Street Lighting0%
Electrical meter r…0%
Water Supply75%
Internal Roads & F…80%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Rudram Infra Projects Private Limited

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Shingdhol
Taluka
Karjat
District
Raigarh
Pincode
410201
Survey no.
Survey No. 60-1, 60-4 at Mauje - Shingdhol, Taluka - Karjat, District - Raigad 410201
North boundary
Survey No 70
East boundary
Survey No 59
South boundary
Survey No 70
West boundary
Boundary of Village Dhotre
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 3.7 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.0 km · Shilhar Nadi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Collector Office Raigad

Collector office
Layout Permit
Survey no. Survey No. 60-1, 60-4 at Mauje - Shingdhol, Taluka - Karjat, District - Raigad 410201
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Collector Office Raigad

Planning authority

Has approved 9 RERA projects0% of Maharashtra.

an apartments market78% apartments · 22% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
9
On record
0 flats · 155 plots
Since
2017

More layout-heavy than Maharashtra overall — 22% plots here vs 5% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.