Complete project overview

MahaRERA · Registration filing
Floors
2
Buildings
13
Land area
8,000 sq m
Sanctioned built-up
3,119 sq m

Timeline

RERA registeredJan 2023
Proposed completionOct 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Street Lighting0%
Electrical meter r…0%
Basement (if any)80%
Plinth80%
Superstructure80%
Internal finishes80%
Flat fit-out80%
Stairs & lifts80%
External finishes80%
OC-readiness80%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE CONSTRUCTION

PartnershipPromoter type
Nashik, MAHARASHTRABased in
26Projects
16Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
797 homeson the public record across 26 projects
52,568 sq mbuilt-up filed
23,736 sq mland declared
₹32.00 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Others3 of 10 projects
Rajkot Municipal CorporationMunicipal / Corporation3 of 10 projects
Bhavnagar Municipal CorporationMunicipal / Corporation1 of 10 projects
Credai Nashikthis project1 of 10 projects
Kolkata Municipal CorporationMunicipal Corporation1 of 10 projects
Rajpur-Sonarpur MunicipalityMunicipality1 of 10 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik (M Corp.)
Taluka
Nashik
District
Nashik
Pincode
422007
Survey no.
SR / CTS NO GAT NO 450/1/1
North boundary
GAT NO 451 AND 452
East boundary
GAT NO 449
South boundary
MOUJE CHUNCHALE SHIV AND 18 MTR ROAD
West boundary
MOUJE TIRADSHETGAON SHIV
What’s nearby
SchoolsNo schools within 2km · College or university 596m away
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.2 km · Trimbakeshwar RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 894 mRiver 4.0 km · Pundi Nadi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Credai Nashik

Building Permit
Survey no. SR / CTS NO GAT NO 450/1/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.