Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
3
Parking
20 spaces
Land area
2,071 sq m
Sanctioned built-up
2,071 sq m

Timeline

RERA registeredApr 2018
Proposed completionMar 2024
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Landscaping & Tree…0%
Energy managemcnt0%
Fire protection an…0%
Open Parking0%
Sewerage (Chamber,…25%
Street Lighting30%
Electrical meter r…30%
Water Supply50%
Water conservation…50%
Basement (if any)95%
Plinth95%
Excavation100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHITOLE CONSTRUCTION

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2018–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimpri Chinchawad (M Corp.)
Taluka
Haveli
District
Pune
Pincode
411027
Survey no.
2711/2714/2715/2716
North boundary
MR DURAKE GURUPRASAD APPARTMENT
East boundary
SANJAY SHITOLE PROPERTY
South boundary
MILITARY AREA
West boundary
GURUPRASAD APPARTMENT
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 414m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 1.7km away · Gym or sports centre 868m away · 6 restaurants and cafes within 1km
ShoppingSupermarket 540m away · Mall 405m away · Bank 625m away
Getting around
Expressway 2.2 km · Old Pune–Mumbai HighwayPrimary road 820 m · Aundh Ravet RoadRailway line 2.1 km · Mumbai–Pune RailwayRailway station 2.1km away (Dapodi)7 bus stops within 500m
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.