Complete project overview

MahaRERA · Registration filing
Floors
22
Buildings
4
Parking
107 spaces
Land area
1,617 sq m
Sanctioned built-up
3,783 sq m

Timeline

RERA registeredJul 2017
Proposed completionDec 2019
TodayJul 2026
Construction progress
OC-readiness10%
Water Supply25%
Fire protection an…30%
Electrical meter r…50%
Flat fit-out75%
Sewerage (Chamber,…90%
Internal finishes95%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
External finishes100%
Storm Water Drains100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Chetna Global

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400080
Survey no.
1109/2A, 1109/2B, 1109/3
North boundary
Lala Devidayal Road
East boundary
Existing Road
South boundary
Layout Road
West boundary
Meghal Industrial Estate
What’s nearby
Schools3 schools within 1km · 5 educational institutions within 1km · College or university 327m away
HealthcareHospital 186m away · 8 clinics within 1km · Pharmacy within 500m
LifestylePark 1.2km away · Gym or sports centre 597m away · 38+ restaurants and cafes within 1km
ShoppingSupermarket 748m away · Mall 1.2km away · Convenience store within 1km
Getting around
Expressway 2.4 kmPrimary road 131 m · Lal Bahadur Shastri MargRailway line 1.3 km · Central Railways Fast LineRailway station 1.4km away (Mulund)24 bus stops within 500m
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 1109/2A, 1109/2B, 1109/3

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.