MahaRERA · Registration filing
Floors
13
Buildings
2
Parking
263 spaces
Land area
4,147 sq m
Sanctioned built-up
14,016 sq m
Recreational open space
717 sq m

Timeline

RERA registeredMar 2025
Proposed completionDec 2029
TodayJul 2026
Construction progress
Podiums0%
Internal finishes0%
Flat fit-out0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Fire protection an…0%
Electrical meter r…0%
External finishes3%
OC-readiness4%
Stairs & lifts26%
Stilt floor50%
Superstructure54%
Basement (if any)60%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

BHAVESHWAR INFRA

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kamothe
Taluka
Panvel
District
Raigarh
Pincode
410209
Survey no.
PLOT NO 32 SECTOR 25
North boundary
20 MTR WIDE ROAD
East boundary
PLOT NO 31
South boundary
PLOT NO 33 34 AND 35
West boundary
20 MTR WIDE ROAD
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 522m away · 1 clinic within 1km
LifestylePark 976m away · Gym or sports centre 1.7km away
ShoppingSupermarket 566m away
Getting around
Expressway 262 m · Uran Road FlyoverPrimary road 389 mRailway line 378 m · Harbour LineRailway station 511m away (Khandeshwar)Bus stop within 1km
Water & environment
Water body 289 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. PLOT NO 32 SECTOR 25
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.