HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Units
88 units
Mix
44 × 1 BHK · 44 × 2 BHK
Carpet area
48–73 sq mper-unit range, as filed
Floors
12
Land area
3,477 sq m
Sanctioned built-up
5,115 sq m
Recreational open space
266 sq m

Timeline

RERA registeredJan 2020
Proposed completionApr 2024
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

88 units across 3 batches
TypeArea sq mCount
1 BHK4844
2 BHK7322
2 BHK7022

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Rainbow Construction

PartnershipPromoter type
Pune, MAHARASHTRABased in
3Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
209 homeson the public record across 3 projects
11,459 sq mbuilt-up filed
7,163 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sus
Taluka
Mulshi
District
Pune
Pincode
411021
Survey no.
SR. NO. 50/1/1 TO 50/1/10
North boundary
ROAD
East boundary
SR NO 50 P
South boundary
SR NO 50P
West boundary
SR NO 49
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
No metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 3.4 km · Kaal River
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.