Complete project overview

MahaRERA · Registration filing
Units
112 units
Mix
80 × 1 BHK · 32 × 2 BHK
Carpet area
38–66 sq mper-unit range, as filed
Floors
10
Buildings
4
Parking
56 spaces
Land area
4,695 sq m
Sanctioned built-up
4,281 sq m
Recreational open space
470 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2023
TodayJul 2026
Construction progress
Podiums0%
Aggregate area of …0%
Sewerage (Chamber,…25%
Water conservation…25%
Electrical meter r…25%
OC-readiness50%
Landscaping & Tree…50%
Solid Waste Manage…50%
Energy managemcnt50%
Flat fit-out60%
Stairs & lifts70%
Internal Roads & F…75%
Fire protection an…75%
Internal finishes90%
External finishes90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Water Supply100%
Street Lighting100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

112 units across 11 batches
TypeArea sq mCount
1 BHK4516
2 BHK6632
1 BHK4316
1 BHK3916
1 BHK384
1 BHK404
1 BHK394
1 BHK384
1 BHK394
1 BHK398
1 BHK394

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

NAYAN BUILDERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
2Cities
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
157 homeson the public record across 2 projects
11,296 sq mbuilt-up filed
8,544 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
UNDRI
Taluka
Haveli
District
Pune
Pincode
411060
Survey no.
19/1/2/2
North boundary
19
East boundary
19
South boundary
18
West boundary
17
What’s nearby
Schools1 school within 500m
HealthcareHospital 812m away
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 864m away · Mall 1.9km away · ATM within 500m
Getting around
Expressway 1.1 kmPrimary road 2.6 km · Kondhwa Main RoadRailway line 3.5 km · Pune - Miraj Railway LineRailway station 3.7km awayLimited bus connectivity nearby
Water & environment
Water body 1.7 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

10 complaints on MahaRERA’s register for this project 9 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.