Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
154 spaces
Land area
1,645 sq m
Sanctioned built-up
5,598 sq m

Timeline

RERA registeredJul 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Electrical meter r…0%
Internal finishes48%
Superstructure55%
Stairs & lifts55%
Stilt floor65%
Plinth90%
Basement (if any)95%
Podiums95%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

MUKESH PREMJI PATEL

IndividualPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kalamboli
Taluka
Panvel
District
Raigarh
Pincode
410218
Survey no.
PLOT NO. 16
North boundary
EXISTING ELECTRICAL LANE
East boundary
TREE BELT
South boundary
PLOT NO-15
West boundary
EXISTING 15 MTR ROAD
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 213m away · 1 clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.7km away
ShoppingSupermarket 501m away
Getting around
Expressway 702 mPrimary road 1.8 kmRailway line 1.4 kmRailway station 1.8km away (Navade Road)Bus stop within 1km
Water & environment
Water body 702 mRiver 811 m · Kasardi RiverCanal 1.3 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Panvel Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO. 16
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Panvel Municipal Corporation

Municipal corporation

Has approved 305 RERA projects1.5% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
238
On record
4,602 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.