CHAKOLAS LAKESIDE
Timeline
Project startedSep 2009
Proposed completionApr 2014
RERA registeredJun 2021
TodaySep 2026
Construction progress
87% overall, as filed
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
2 of 39 available
TypeArea sq mAvailable
3BHK1242 of 24
3BHK1690 of 15
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.
Complete project overview — done
02
Builder’s track record
K-RERA · Builder registration
CHAKOLAS HOMES PVT LTD
CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools1 school within 1km · 3 educational institutions within 1km · Library 368m away
HealthcareHospital 1.2km away · 1 clinic within 1km
LifestylePark 752m away
ShoppingSupermarket 1.9km away · Mall 1.8km away
Getting around
Expressway 1.4 km · IMU JunctionPrimary road 383 m · Old NH 47Railway line 1.9 kmRailway station 2.5km away (Kumbalam)Bus stop within 500mAirport 4.0km away
Water & environment
Water body 118 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Location — done
04
Government Guidance Rate
Kerala Registration Department — fair value
In Kerala it’s called the fair value.
₹6,622per sq yd
₹7,920per sq m
Which rate
Residential Plot with private road access
Matched to
The value published for this project's own survey number, in “Edakochi”.
What this number is — and isn’t
The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of parcel, and says so above. How Horizon decides what to show.
The promised possession date (15 Apr 2014) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Verify it yourself — look up plan SYP1/249/09 dt 17/09/2009 on the approving authority’s portal to confirm the approval.
The approving body, at scale
Kochi Municipal Corporation
Municipal corporation / municipality
Has approved 92 RERA projects — about 1 in 17 in Kerala.
an apartments market — 97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.
Builders
50
On record
4,090 flats · 12 plots
Since
2021
More apartment-heavy than Kerala overall — 97% apartments here vs 81% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
The approving body's other projects: counted by Horizon across the register.
06Complaints & litigation
Cases listed on K-RERA's project page: listed on the project's K-RERA page.
07Other projects nearby
The RERA-registered projects Horizon holds within 25 km of these coordinates.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/chakolas-lakeside-edakochi-ernakulam-zk2x7nxg.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.