Complete project overview

MahaRERA · Registration filing
Floors
66
Buildings
4
Parking
1,400 spaces
Land area
1,549 sq m
Sanctioned built-up
15,764 sq m

Timeline

RERA registeredJan 2023
Proposed completionDec 2028
TodayJul 2026
Construction progress
Flat fit-out40%
OC-readiness40%
Water Supply40%
Landscaping & Tree…40%
Solid Waste Manage…50%
Energy managemcnt50%
Electrical meter r…50%
Treatment And Disp…60%
Water conservation…60%
Fire protection an…65%
External finishes70%
Sewerage (Chamber,…70%
Internal finishes75%
Stairs & lifts75%
Storm Water Drains80%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

CHANDAK REALTORS PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
5Projects
3Cities
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
5 projectson the public record across 5 projects
2,56,410 sq mbuilt-up filed
65,948 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project3 of 5 projects
Slum Rehabilitation AuthoritySlum Rehabilitation Authority2 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Chinchvali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400064
Survey no.
838 (pt) village of Malad W and 13 village of chinchavli
North boundary
Land bearing CTS No 838 part
East boundary
Land bearing CTS No 12 A 2B 1
South boundary
18 30 meters wide east west DP Road
West boundary
18 30 meters wide north south DP Road
What’s nearby
Schools1 school within 500m · College or university 1.6km away
HealthcareHospital 47m away · 7 clinics within 1km · Pharmacy within 1km
LifestylePark 1.2km away · Gym or sports centre 1.1km away · 9 restaurants and cafes within 1km
ShoppingSupermarket 1.1km away · Mall 1.0km away · Bank 682m away
Getting around
Expressway 1.6 km · Pathanwadi FlyoverPrimary road 366 m · Swami Vivekanand RoadRailway line 611 m · Western Railway (Slow)Metro station 960m away (Lower Malad)Bus stop within 1km
Water & environment
Water body 603 m · Bhujawale LakeRiver 621 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 838 (pt) village of Malad W and 13 village of chinchavli
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation2 cases on record, earliest 2010
EncumbranceDeclared financial encumbrance on the project
Compliance3 non-compliance notices on record
Appeals1 appeal before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

6 complaints on MahaRERA’s register for this project 5 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.