HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Land area
1,185 sq m
Sanctioned built-up
5,266 sq m

Timeline

RERA registeredMar 2022
Proposed completionSep 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Flat fit-out0%
External finishes0%
Sewerage (Chamber,…0%
Water conservation…0%
Fire protection an…0%
Water Supply10%
Stairs & lifts50%
OC-readiness50%
Basement (if any)75%
Internal finishes75%
Excavation100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHRI AMARNATH BUILDERS AND DEVELOPERS

PartnershipPromoter type
Amravati, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Amravati (M Corp.)
Taluka
Amravati
District
Amravati
Pincode
444606
Survey no.
PLOT NO 1 OF F.S. NO.218 AT MOUJE RAHATGAON
North boundary
RING ROAD
East boundary
OTHER LAYOUT
South boundary
OTHER LAYOUT
West boundary
18 MTR WIDE ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Convenience store within 500m · ATM within 500m
Getting around
Expressway 124 m · Amravati BypassPrimary road 647 mRailway line 4.7 kmRailway station 4.9km away (Amravati)Limited bus connectivity nearby
Water & environment
Water body 3.7 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Amravati Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO 1 OF F.S. NO.218 AT MOUJE RAHATGAON
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Amravati Municipal Corporation

Municipal corporation

Has approved 57 RERA projects0.3% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
56
On record
467 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.