01

Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
2
Parking
371 spaces
Land area
2,804 sq m
Sanctioned built-up
4,269 sq m

Timeline

RERA registeredSep 2023
Proposed completionMar 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Street Lighting0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Flat fit-out10%
External finishes10%
OC-readiness20%
Internal finishes25%
Stairs & lifts25%
Superstructure80%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Rathod & Sons

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
6,237 sq mbuilt-up filed
8,404 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimpale Gurav
Taluka
Haveli
District
Pune
Pincode
411061
Survey no.
84/1/12A and 85/1B/1P, CTS 2044P 2460 2461 2463P Pimple Gurav
North boundary
By Road
East boundary
By remaining property of Balu ramchandra Jawalkar
South boundary
By Road
West boundary
By Road
What’s nearby
SchoolsNearest school 1.6km away
HealthcareHospital 54m away · 1 clinic within 1km
Lifestyle1 park within 500m · Gym or sports centre 396m away · 10+ restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Mall 275m away
Getting around
Expressway 1.0 kmPrimary road 222 mRailway line 931 m · Mumbai–Pune RailwayRailway station 1.1km away (Kasarwadi)Bus stop within 500m
Water & environment
River 302 m · Pavana RiverWater body 504 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 84/1/12A and 85/1B/1P, CTS 2044P 2460 2461 2463P Pimple Gurav

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.