HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
88 spaces
Land area
1,620 sq m
Sanctioned built-up
6,244 sq m

Timeline

RERA registeredAug 2024
Proposed completionDec 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Water conservation…0%
Electrical meter r…0%
Internal finishes30%
Stairs & lifts30%
External finishes40%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SETHI INFRA

PartnershipPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vasai-Virar City (M Corp)
Taluka
Vasai
District
Palghar
Pincode
401202
Survey no.
S. NO. 70/4/2
North boundary
OPEN SPACE
East boundary
S NO 70 H NO 4 1
South boundary
20 MTR WIDE ROAD
West boundary
9 MTR WIDE ROAD
What’s nearby
SchoolsNearest school 1.2km away
HealthcareHospital 83m away · 6 clinics within 1km
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Primary road 677 m · Bassein RoadRailway line 1.2 kmRailway station 1.2km away (Vasai Road)Limited bus connectivity nearby
Water & environment
Water body 424 mRiver 1.5 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Vasai Virar City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S. NO. 70/4/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Vasai Virar City Municipal Corporation

Municipal corporation

Has approved 627 RERA projects3.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
513
On record
8,010 flats · 60 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.