Complete project overview

RERA Delhi · Registration filing
Land area
39,400 sq m
Mega project
Yesregistered under Delhi RERA's mega-project category — a scale classification the authority records, not a rating

Timeline

Project startedMay 2015
Proposed completionJun 2019
TodayJul 2026
02

Builder’s track record

RERA Delhi · Promoter registration

DELHI DEVELOPMENT AUTHORITY

Development AuthoritiesPromoter type
24Projects
1Cities
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4,315 homeson the public record across 24 projects
1,14,401 sq mbuilt-up filed
9,51,520 sq mland declared
₹1418.89 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Delhi · Registration filing
District
South West Delhi
Address
Adjacent to pocket-3 sector-19B , Dwarka, New Delhi Dwarka , South West Delhi , Delhi - 110075
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 1.7km away · 3 clinics within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.9km away
ShoppingSupermarket 1.4km away · Convenience store within 500m
Getting around
Expressway 1.8 km · Urban Extension Road-IIPrimary road 3.6 km · Rd. No. 224Railway line 3.4 kmMetro station 1.4km away (Dwarka Sector 11)Limited bus connectivity nearby
Water & environment
River 620 m · Sahibi RiverWater body 815 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipDeclared fully owned by the promoter
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

RERA Delhi · Approved building plan
Building Permit

The promised possession date (10 Jun 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Delhi does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Delhi does not publish a complaints register. This read cannot speak to them either way.