HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
18,400 sq m
Description
Project is having 80 Plots, 7 commercial & 8 Informal commercial shop. Since our project is new we have not appointed any contractor till now. As soon as we will appoint we will inform to RERA. Since the project is not in Phases we have only given Name Coral Park Phase A.

Timeline

Construction startMar 2018
RERA registeredApr 2018
Proposed completionSep 2019
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

coral associates

OrganisationPromoter type
Kota, RajasthanBased in
4Projects
1City
2018–2021Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4 projectson the public record across 4 projects
73,200 sq mplotted area
73,200 sq mland declared
₹38.50 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
59, 60, 346/60 (Part) & 347/60, BARAN ROAD, HANUWANT KHERA, Ladpura, Kota, 324001
Village
HANUWANT KHERA
Taluka
Ladpura
District
Kota
Pincode
324001
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 779m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 676 m · Kota BypassPrimary road 3.5 kmRailway line 4.2 km · Mumbai - Delhi RailwayRailway station 4.9km away (Chandresal)Limited bus connectivity nearby
Water & environment
River 997 mCanal 4.0 kmWater body 4.7 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹8.00 Cr declared. What that works out to:

₹404/sq ftof plotted area₹4,348/sq m
63%of the cost is land₹252/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Layout Permitapproved 6 Apr 2018 · 8 yrs ago

The promised possession date (26 Sep 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.