Complete project overview

MahaRERA · Registration filing
Units
27 units
Mix
19 × Unit · 5 × Shop · 3 × Office
Carpet area
8–117 sq mper-unit range, as filed
Floors
26
Parking
84 spaces
Land area
1,447 sq m
Sanctioned built-up
4,485 sq m
Recreational open space
528 sq m

Timeline

RERA registeredFeb 2024
Proposed completionMay 2027
TodayJul 2026
Construction progress
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Flat fit-out5%
Internal finishes10%
Superstructure25%
Stairs & lifts25%
Podiums50%
Basement (if any)90%
Plinth90%
Stilt floor90%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

27 units across 23 batches
TypeArea sq mCount
Unit271
Office501
Office1121
Office731
Shop801
Unit81
Unit91
Unit171
Unit191
Shop211
Unit211
Shop361
Unit234
Unit281
Unit301
Unit531
Unit671
Unit671
Unit721
Unit741
Unit981
Unit1171
Shop272

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Satish Chimanlal Dedhia

IndividualPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mulund
Taluka
Kurla
District
Mumbai Suburban
Pincode
400080
Survey no.
1175,1175/1 to 17
North boundary
13 Mt Wide Ganesh Gavde Road
East boundary
18 Mt Wide Ramratan Trivedi Road
South boundary
Mulund Night High School
West boundary
Mahamaya Bhuvan
What’s nearby
Schools3 schools within 500m · 7 educational institutions within 1km · College or university 996m away
HealthcareHospital 38m away · 14 clinics within 1km · Pharmacy within 1km
LifestylePark 1.0km away · Gym or sports centre 956m away · 58+ restaurants and cafes within 1km
ShoppingSupermarket 450m away · Mall 922m away · Convenience store within 1km
Getting around
Expressway 1.7 km · Kopri FlyoverPrimary road 693 m · Lal Bahadur Shastri MargRailway line 702 m · Central Railways Slow LineRailway station 720m away (Mulund)25 bus stops within 500m
Water & environment
Water body 866 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 1175,1175/1 to 17
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2024
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.