HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
29
Buildings
2
Land area
1,744 sq m
Sanctioned built-up
9,034 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2022
TodayJul 2026
Construction progress
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Stairs & lifts10%
Superstructure30%
Podiums50%
Stilt floor50%
Excavation90%
Basement (if any)90%
Plinth90%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

S. D. Bhalerao Associates

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
VARTAKNAGAR
Taluka
Thane
District
Thane
Pincode
400606
Survey no.
211, 212
North boundary
By 30 Feet Road
East boundary
By 30 Feet wide Road
South boundary
By Building No 49
West boundary
By Open Space
What’s nearby
Schools1 school within 1km · Library 900m away
HealthcareHospital 245m away · 2 clinics within 1km
LifestylePark 569m away · Gym or sports centre 797m away
ShoppingSupermarket 1.5km away · Mall 957m away · Bank 464m away
Getting around
Expressway 1.1 kmPrimary road 1.6 km · Lal Bahadur Shastri MargRailway line 1.6 kmMetro station 2.1km away (Kapurbawdi Station)12 bus stops within 500m
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 211, 212

The promised possession date (30 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Compliance8 non-compliance notices on record
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

14 complaints on MahaRERA’s register for this project 13 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.