01
Complete project overview
MahaRERA · Registration filing- Floors
- 8
- Buildings
- 5
- Parking
- 99 spaces
- Land area
- 7,000 sq m
- Sanctioned built-up
- 10,029 sq m
- Recreational open space
- 700 sq m
Timeline
RERA registeredNov 2018
Proposed completionOct 2024
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Internal Roads & F…10%
Water Supply25%
Sewerage (Chamber,…25%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
02
Builder’s track record
MahaRERA · Promoter registrationJAY DESHMUKH CONSTRUCTION
PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2018–2024Active
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Baramati Rural
- Taluka
- Baramati
- District
- Pune
- Pincode
- 413102
- Survey no.
- 247
- North boundary
- 247
- East boundary
- 251
- South boundary
- 247
- West boundary
- 247
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 652m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 133 m · Patas RoadPrimary road 743 m · Jejuri Morgaon Baramati RoadRailway line 1.2 kmRailway station 1.2km away (Baramati)Limited bus connectivity nearby
Water & environment
River 437 m · Karha RiverWater body 871 mCanal 893 m
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.