HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
4
Buildings
8
Parking
36 spaces
Land area
1,983 sq m
Sanctioned built-up
2,610 sq m

Timeline

RERA registeredOct 2025
Proposed completionJul 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Superstructure20%
Plinth90%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

D R GAVHANE LANDMARKS LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
13Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
485 homes · 83 plotson the public record across 13 projects
67,905 sq mbuilt-up filed
11,640 sq mplotted area
34,183 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Charoli
Taluka
Haveli
District
Pune
Pincode
412105
Survey no.
S No 495/9 P Charholi Budruk
North boundary
By Remaining Property Of Satyawan Kalje From Survey No 495/8
East boundary
By Remaining Property From Survey No 495/9
South boundary
By Remaining Property Of Nilesh Popat Kalje From Survey No 495/5
West boundary
By Remaining Property Of Prakash Kalje From Survey No 495/5
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.6km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 2.1 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 385 mWater body 571 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S No 495/9 P Charholi Budruk
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.