Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
2
Parking
61 spaces
Land area
3,950 sq m
Sanctioned built-up
6,910 sq m
Recreational open space
395 sq m

Timeline

RERA registeredFeb 2023
Proposed completionDec 2026
TodayJul 2026
Construction progress
Water Supply0%
Energy managemcnt0%
Aggregate area of …0%
Street Lighting50%
Flat fit-out80%
Internal Roads & F…85%
Treatment And Disp…85%
Landscaping & Tree…90%
Stilt floor95%
Internal finishes95%
Stairs & lifts95%
External finishes95%
OC-readiness95%
Sewerage (Chamber,…95%
Storm Water Drains95%
Fire protection an…95%
Electrical meter r…95%
Basement (if any)97%
Podiums97%
Excavation100%
Plinth100%
Superstructure100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

EL PROGRESO LANDMARKS

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimpri Chinchawad (M Corp.)
Taluka
Haveli
District
Pune
Pincode
412105
Survey no.
GAT NO 75 BORHADEWADI
North boundary
BY DESTINATION EL PROGRESO A BUILDING
East boundary
BY BOUNDARY OF PCNTDA
South boundary
BY BOUNDARY OF PCNTDA
West boundary
BY GAT NO 79 OLD GAT NO 1199
What’s nearby
Schools1 school within 1km
HealthcareHospital 128m away · 4 clinics within 1km
LifestylePark 663m away · Gym or sports centre 1.1km away
ShoppingSupermarket 1.9km away · Mall 1.6km away
Getting around
Expressway 617 m · Pimpri Chowk UnderpassPrimary road 611 m · UnderpassRailway line 89 m · Mumbai–Pune RailwayRailway station 491m away (Pimpri)Limited bus connectivity nearby
Water & environment
River 819 m · Pavana RiverWater body 952 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. GAT NO 75 BORHADEWADI
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2021
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.