01
Complete project overview
MahaRERA · Registration filing- Floors
- 19
- Buildings
- 2
- Parking
- 124 spaces
- Land area
- 1,363 sq m
- Sanctioned built-up
- 7,037 sq m
Timeline
RERA registeredJan 2025
Proposed completionDec 2029
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
02
Builder’s track record
MahaRERA · Promoter registrationK.S. Builders and Developers
PartnershipPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Vasai-Virar City (M Corp)
- Taluka
- Vasai
- District
- Palghar
- Pincode
- 401203
- Survey no.
- 271/6
- North boundary
- ANAND PARK CHS LTD
- East boundary
- TRINITY HEIGHTS CHS LTD
- South boundary
- KISAN CHS LTD
- West boundary
- D D COMPLEX CHS LTD
What’s nearby
Schools1 school within 1km
HealthcareHospital 507m away · 4 clinics within 1km
LifestylePark 602m away · Swimming pool within 2km
ShoppingSupermarket 1.1km away · Convenience store within 1km · Bank 772m away
Getting around
Primary road 288 m · Central Park RoadRailway line 415 mRailway station 890m away (Nalla Sopara)2 bus stops within 500m
Water & environment
Water body 1.3 km
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
1 complaint on MahaRERA’s register for this project — 1 disposed.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.