Complete project overview

MahaRERA · Registration filing
Floors
10
Buildings
2
Parking
1 spaces
Land area
1,075 sq m
Sanctioned built-up
3,222 sq m

Timeline

RERA registeredAug 2017
Proposed completionJul 2023
TodayJul 2026
Construction progress
Podiums0%
Plinth0%
Solid Waste Manage…0%
Fire protection an…0%
Electrical meter r…0%
Flat fit-out10%
Stairs & lifts55%
External finishes55%
OC-readiness55%
Water Supply55%
Sewerage (Chamber,…55%
Storm Water Drains55%
Superstructure64%
Internal finishes65%
Stilt floor75%
Excavation100%
Basement (if any)100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

DHUNJIBHOY ICE FACTORY PVT. LTD.

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2017–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mumbai City
Taluka
Mumbai City
District
Mumbai City
Pincode
400010
Survey no.
6124
North boundary
124
East boundary
312
South boundary
NESBIT ROAD
West boundary
124
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.5km away
HealthcareHospital 289m away · Clinic within 2km
LifestylePark 1.5km away
ShoppingNo supermarket within 2km · Mall 1.5km away · Bank 22m away
Getting around
Expressway 931 m · Dr Babasaheb Ambedkar MargPrimary road 397 m · Barrister Nath Pai MargRailway line 334 m · Central Railway (Harbour Line)Railway station 372m away (Dockyard Road)6 bus stops within 500m
Water & environment
Water body 628 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 6124

The promised possession date (31 Jul 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.