Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Parking
36 spaces
Land area
544 sq m
Sanctioned built-up
1,414 sq m

Timeline

RERA registeredFeb 2024
Proposed completionJul 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Water conservation…0%
Electrical meter r…0%
Flat fit-out25%
External finishes35%
Stilt floor50%
Internal finishes50%
Stairs & lifts50%
Excavation90%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

DEEPAK BHALCHANDRA MHATRE

IndividualPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400605
Survey no.
1012
North boundary
EXISTING BUILDING
East boundary
EXISTING BUILDING
South boundary
EXISTING BUILDING
West boundary
BELAPUR ROAD
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 180m away
LifestyleNo parks within 2km · Gym or sports centre 155m away
ShoppingNo supermarket within 2km · Bank 154m away · ATM within 500m
Getting around
Expressway 682 mPrimary road 1.6 km · Saket FlyoverRailway line 176 mRailway station 1.0km away (Kalva)10 bus stops within 500m
Water & environment
Water body 152 m · Kharegaon LakeCanal 1.0 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Assistant Director Town Planning, Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 1012
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.