HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
19 spaces
Land area
429 sq m
Sanctioned built-up
1,158 sq m

Timeline

RERA registeredDec 2022
Proposed completionApr 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

DHIRAJ narayandas JADHWANI

IndividualPromoter type
Mumbai Suburban, MAHARASHTRABased in
3Projects
1City
2020–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
22 homeson the public record across 3 projects
2,667 sq mbuilt-up filed
1,281 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400074
Survey no.
359,360
North boundary
358
East boundary
350
South boundary
361
West boundary
410
What’s nearby
SchoolsNearest school 1.7km away · College or university 1.9km away · Library 1.9km away
HealthcareHospital 163m away · 1 clinic within 1km
LifestylePark 837m away · Gym or sports centre 990m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Bank 923m away
Getting around
Expressway 1.2 kmPrimary road 1.4 km · Padmabushan Vasantdada Patil MargRailway line 395 mRailway station 177m away (Fertilizer Township)2 bus stops within 500m
Water & environment
Water body 548 m · Ashish Talao
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 359,360

The promised possession date (1 Apr 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.